Sl. No. Name of the project Completion Time
1 Construction of 132/33 kV & 33/11kV SS under DPDC (132/33 kV Substation at Kazla, New Ramna, Postogola, Bangabhaban, Char Sayedpur, Khanpur and Panthapath.
33/11 kV Substation at D I T, Segun bagicha, Mirhazirbag, Jurain Mazar/Alam Market, Albart David, Maa O Shishu, Konapara, Jatrabari PDB Colony, Monipuripara, Karwan Kancha Bazar, Green Road Dormitory, Kamalapur Railway Hospital, Kamalapur 11 kV SW/S, Nandalalpur & Laxminarayan Cotton Mill)
2015-2016
2 Construction & Expansion of Distribution Network of North & South Zone under DPDC 2015-2016
3 Efficiency Energy for DPDC Distribution Network by the System Metering Project 2015-2016
4 Reactive Power Compensation of DPDC Network
(Kamrangirchar, Moghbager, Dhanmondi, Narinda, Ullon, Saidabadh, Shyampur, Shitalakhya, Matuail)
2014-2015
5 Prepayment Metering Project for 6 NOCS Division under DPDC.
(Lalbag, Basaboo, Maniknagar, Bangshal, Jurain, Narayanganj (East)
2014-2015
6 Prepayment Metering Project for 8 NOCS Division under DPDC.
(Jigatola, Azimpur, Kakrail, Khilgaon, Narayangonj(W), Mugdapara, Banglabazar, Postagola.)
2015-2016
7 Construction of 6 nos. 33/11 kV Substation for Power System of DPDC.
(DPDC’s own fund)
(6 nos. of substation in Baily Road, P&T, Banasree, B B Avenue, Dhaka Udyan, Mugdapara Hospital)
2015-2016
8 Pre-payment Metering Project for 9 nos. NOCS Division under DPDC (Phase-1) 2017-2018
9 Reactive Power Compensation at 33/11 kV Substation under DPDC 2017-2018
10 Conversion of 15 Nos. 33/11 kV switching station to a regular 33/11 kV SS under DPDC Area.
(Narinda, Dhaka Jail, Asad Gate, Hazaribag, P & T, Baily Road, Sikdar Medical, Mugdapara, Hatkhola, LNCM, Monipuripara, AlbertDavid (Postagola), DIT, Water Works, Eidgah)
2019-2020
11 Construction of 3 nos. 132/33 KV Grid S/S under DPDC. 2020-2021
12 Pre-payment Metering Project for 9 nos. NOCS Division under DPDC (Phase-2) 2020-2021